Mesquite Gold Mine

Producing gold in California

Mesquite has been operating since 1986 as an open-pit heap leach mine.

Snapshot

Ownership

100%

Location

California, USA

2024 Production1

75,000-85,000 oz gold

2023 Costs1

$1,410-$1,510 per oz AISC

Reserves

471 Koz @ 0.48 g/t gold

M&I Resources2

1,384 Koz @ 0.41 g/t gold

Mining and processing

Open-pit / heap leach

Estimated mine life

~2 years + residual leaching

1. Guidance released on February 21, 2024.
2. M&I Mineral Resources are exclusive of Mineral Reserves. See Operations / Reserves & Resources and Cautionary Notes.

Overview

Mesquite is an open pit, run-of-mine heap leach gold mine located in Imperial County, California, USA, approximately 200 miles south of our Castle Mountain Mine, 16 miles west of the state border with Arizona and 24 miles north of the border with Mexico. Mesquite has produced more than five million ounces of gold since it commenced operations in 1986, with annual gold production averaging approximately 125,000 ounces over the last 10 years.

Mesquite was Equinox Gold’s first operating mine. The Company acquired Mesquite in October 2018, immediately transforming Equinox Gold from a developer to a gold producer. Since then, strong gold prices and exploration success have significantly extended the mine life, bringing consistent cash flow to the Company and substantial value to Equinox Gold shareholders.

Inflationary pressures during 2022 hit Mesquite particularly hard, since the mine’s most significant consumables of diesel, cyanide and lime experienced massive price increases. To reduce costs during 2023, mining at Mesquite has pivoted to a small-pit approach to reduce waste stripping. While this will reduce production in 2023, exploration and permitting will continue to enable mine life extensions beyond 2023.

Production at Mesquite in 2024 is forecast at 75,000 – 85,000 ounces of gold with all-in sustaining costs between $1,410 to $1,510 per ounce of gold sold.

Operating Data

 2023 Actuals2022 Actuals2021 Actuals2020 Actuals
Gold produced (oz)87,753123,965137,467141,270
Cash costs ($/oz)1,105978974899
AISC ($/oz)1,251 1,2851,3271,091
Sustaining capital ($M)11 364624
Growth capital ($M) 1718199

Mining and Processing

Mining is performed using owner-operated, conventional truck and shovel open pit mining methods. Run-of-mine ore is hauled directly to the leach pad for processing, with a standard carbon-in-column circuit to recover gold. While the Company is mining one ore body, it commences waste stripping of a new deposit to provide the next source of ore. Equinox Gold is currently stripping two new ore bodies that will provide ore during 2023. 

Gold recoveries average approximately 75% for oxide ore and 35% for non‐oxide ore, with a 90-day leach cycle. Residual leaching of previously leached ore is anticipated to continue for two to three years after final ore is placed, providing continued gold production even after mining has ceased.

Exploration and Geology

Since acquiring Mesquite in 2018, Equinox Gold has significantly extended the mine life by drilling historical waste dumps and historical leach pads to identify mineralization that is economic at current gold prices. In addition, there are a number of exploration targets within the Mesquite mine boundary, both within and adjacent to existing open pits. Ongoing efforts at Mesquite are focused on Mineral Resource growth at the Brownie, Vista East 2 and Rainbow deposits, as well as the conversion of Mineral Resources to Mineral Reserves via metallurgical test work, heap leach optimization studies, and the assessment and design of new leach pads to support mine life extension. 

The Mesquite Mine district lies on the southwest flank of the Chocolate Mountains, in amphibolite grade metamorphic rocks of the upper plate of the Vincent‐Chocolate Mountain Thrust. The Mesquite Mine comprises two subparallel, Oligocene‐age deposits: Big Chief-Vista and Rainbow. Gold mineralization is hosted in Mesozoic gneisses that are intruded by biotite/muscovite rich granites. The district is covered by a thin veneer (up to 300 feet) of Tertiary and Quaternary sediments, shed from the south slope of the Chocolate Mountains. Gold mineralization is bound by post‐mineral faulting related to the San Andreas fault system.

Operating Mines

An Americas-focused gold producer

Equinox Gold has seven operating mines in the USA, Mexico and Brazil.

View our operating mines